Dartmouth Visual Art Center, Phase 2

Here is an aerial view of the Dartmouth Visual Art Center at the end of construction phase 2. Our crew of four guys has worked double shifts using light towers to complete this phase of the installation on schedule. It is amazing to think of all the work our crew has completed in such a tight space. Everyone on the crew who hasn’t been a part of this process is excited to see the finished landscape! We have all heard a lot about each and every aspect of the project and it is going to be beautiful. The crew also received the second and third loads out of eight total (+/- 180 cubic yards), of sand based structural soils for phase 3. We have imported approximately 650 cubic yards of four types of soil for the project. It is incredible to think of the amount of material that is brought in to complete each and every large scale installation.